We are pleased to share the latest construction progress on the GAIA project:
- Major Earthworks are complete, 1 tower crane is ready for use.
- Concrete Work is progressing well.
- Raft for blocks B, C, D and E completed.
- Ground Floor slab for blocks C and E completed, work in progress for blocks B
and D.
- Level 1 slab for block E completed, work in progress for block C.
- Superstructure should be completed for all 5 blocks by the end of July 2025.
- Masonry is planned for December 2024.
The project is on schedule and should be completed by December 31, 2026.