GAIA Construction Dynamics

November 29, 2024

We are pleased to share the latest construction progress on the GAIA project:

- Major Earthworks are complete, 1 tower crane is ready for use.

- Concrete Work is progressing well.

- Raft for blocks B, C, D and E completed.

- Ground Floor slab for blocks C and E completed, work in progress for blocks B

and D.

- Level 1 slab for block E completed, work in progress for block C.

- Superstructure should be completed for all 5 blocks by the end of July 2025.

- Masonry is planned for December 2024.

The project is on schedule and should be completed by December 31, 2026.